RESPONSE BOAT - MEDIUM SYSTEM
CONTRACT DATA REQUIREMENTS LIST
CONTRACT NO: HSCG23-06-D-ARB001 (See Section J - SOW 041-2)


BLK01-SEQUENCE NO.:

070-004 (Orig)

BLK03-SUBTITLE:

Fire, Flooding, and Destructive Weather Plan

BLK04-AUTHORITY:

Technical Report - Study/Services (DI-MISC-80508A)

BLK05-CONTRACT REF:

SOW 070-6.1

BLK07-DD 250 REQUIRED:

LT

BLK08-APP CODE:

A

BLK09-DIST STMT REQD:

C

BLK10-FREQUENCY:

ONE/R

BLK12-DATE OF 1ST SUBM:

60 DAC

BLK13-DATE OF SUBS SUBM:

30 DARC

BLK14-DISTRIBUTION:

Electronic Copy: IPDE
Hard Copies: None

BLK15-TOTAL:

Electronic Copy: Yes
Hard Copies: 0

BLK16-REMARKS:

BLK04: The DID is modified as follows:

Replace paragraph 2 with: Provide, in the Contractor's format, the Fire, Flooding, and Destructive Weather plan or plans for each organization or facility where final assembly of the RB-M occurs, including any subcontractor sites.

ATTACHMENTS:

None