RESPONSE BOAT - MEDIUM SYSTEM
CONTRACT DATA REQUIREMENTS LIST
CONTRACT NO: HSCG23-06-D-ARB001 (See Section J - SOW 041-2)


BLK01-SEQUENCE NO.:

070-002 (Orig)

BLK03-SUBTITLE:

Oil Discharge Report

BLK04-AUTHORITY:

Oil Discharge Report (DI-MGMT-81060)

BLK05-CONTRACT REF:

SOW 070-2.6

BLK07-DD 250 REQUIRED:

LT

BLK08-APP CODE:

BLK09-DIST STMT REQD:

F

BLK10-FREQUENCY:

ASREQ

BLK12-DATE OF 1ST SUBM:

See BLK 16

BLK13-DATE OF SUBS SUBM:

BLK14-DISTRIBUTION:

Electronic Copy: IPDE
Hard Copies: None

BLK15-TOTAL:

Electronic Copy: Yes
Hard Copies: 0

BLK16-REMARKS:

BLK04: Modify DID as follows:
In Paragraph 10.4.8, after “considered germane” insert “including damages resulting from the discharge and remedies taken to correct the damages”.

BLK10: IAW SOW 070-2.

BLK12: Within 24 hours after each discharge of oil and oily or hazardous substance.

ATTACHMENTS: