RESPONSE BOAT - MEDIUM SYSTEM
CONTRACT DATA REQUIREMENTS LIST
CONTRACT NO: HSCG23-06-D-ARB001 (See Section J - SOW 041-2)


BLK01-SEQUENCE NO.:

068-005 (Orig)

BLK03-SUBTITLE:

Engineering Change Proposals (ECP)

BLK04-AUTHORITY:

Engineering Change Proposal (ECP) (DI-CMAN-80639C), Notice of Revision (NOR) (DI-CMAN-80642C), Specification Change Notice (SCN) (DI-CMAN-80643C)

BLK05-CONTRACT REF:

SOW 068-2.3.2

BLK07-DD 250 REQUIRED:

LT

BLK08-APP CODE:

A

BLK09-DIST STMT REQD:

E

BLK10-FREQUENCY:

ASREQ

BLK12-DATE OF 1ST SUBM:

See BLK 16

BLK13-DATE OF SUBS SUBM:

30 DARC, See BLK 16

BLK14-DISTRIBUTION:

Electronic Copy: IPDE
Hard Copies: None

BLK15-TOTAL:

Electronic Copy: Yes
Hard Copies: 0

BLK16-REMARKS:

BLK04: Modify DID as follows:
Replace all references of DID version "B" with version "C".

BLK08: Approval will be based on Government evaluation of the proposed changes which shall be used as the basis for the contract modification. Upon ECP approval, Contractor shall submit NOR or SCN, as appropriate, within 30 days after ECP approval.

BLK10: IAW SOW 068-2.3.

BLK12: 30 days after each need for change is identified. Allow 90 days for Government review.

BLK13: Allow 30 days for Government review.

ATTACHMENTS:

None