RESPONSE BOAT - MEDIUM SYSTEM
CONTRACT DATA REQUIREMENTS LIST
CONTRACT NO: HSCG23-06-D-ARB001 (See Section J - SOW 041-2)


BLK01-SEQUENCE NO.:

041-004 (Orig)

BLK03-SUBTITLE:

Integrated Master Plan (IMP)

BLK04-AUTHORITY:

Management Plan (DI-MGMT-80004)

BLK05-CONTRACT REF:

SOW 041-8.1

BLK07-DD 250 REQUIRED:

LT

BLK08-APP CODE:

A

BLK09-DIST STMT REQD:

C

BLK10-FREQUENCY:

ASREQ

BLK12-DATE OF 1ST SUBM:

See BLK16

BLK13-DATE OF SUBS SUBM:

See BLK16

BLK14-DISTRIBUTION:

Electronic Copy: IPDE
Hard Copies: None

BLK15-TOTAL:

Electronic Copy: Yes
Hard Copies: 0

BLK16-REMARKS:

BLK04: Modify DID as follows:
Replace all occurrences of "management plan" with "Integrated Master Plan". DID paragraph 10.2.c: Delete all but the following text "The pages shall be sequentially numbered. All attachments shall be identified and referenced in the text. Each section and paragraph shall be numbered."
Delete DID paragraph 10.3.5.b.
Delete DID paragraph 10.3.7.

BLK10: Submissions are required in conjunction with each IBR, described in SOW 041-10.2.

BLK12: 15 DBIBR, Allow 15 days for Government Review

BLK13: 15 DARC, Allow 15 days for Government review.

ATTACHMENTS:

None