Orders Against the RB-M Production Contract

Date Order Number Description
21JUN2006 HSCG23-06-J-ARP019 Initial delivery order for Project Management (twelve months of CLIN 1001)
24AUG2006 HSCG23-06-J-ARP021 Delivery order for Detailed Design of RB-M System (CLIN 1002)
17AUG2007 HSCG23-06-J-ARP021/A00001 Modifies delivery order to add interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
06SEP2007 HSCG23-06-J-ARP021/A00002 Modifies delivery order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18OCT2007 HSCG23-06-J-ARP021/A00003 Modifies delivery order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
11JAN2008 HSCG23-06-J-ARP021/A00004 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18MAR2008 HSCG23-06-J-ARP021/A00005 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18MAR2008 HSCG23-06-J-ARP021/A00006 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
17SEPT2008 HSCG23-06-J-ARP021/A00007 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
08SEP2006 HSCG23-06-J-ARP033 Delivery order for first RB-M, 45601 (CLIN 1003A) and additional Project Management (three months of CLIN 2001)
08SEP2006 HSCG23-06-J-ARP034 Delivery order for five RB-M, 45602 thru 45606 (CLIN 1003A) and additional Project Management (nine months of CLIN 1002, three months of CLIN 3001)
23MAR2007 HSCG23-06-J-ARP032 Delivery order for enhancements to Mock-Up (CLIN 1009)
08JUN2007 HSCG23-06-J-ARP032/A00001 Modifies delivery order for implementation of RB-M Agreement 1 (CLIN 1009)
30AUG2007 HSCG23-06-J-ARP032/A00002 Modifies delivery order to definitize REA-001 entitled, "Mock-Up Changes" (CLIN 1009)
5AUG2008 HSCG23-06-J-ARP032/A00003 Modifies delivery order to provide interim funding under CLIN 1009 as changed by Mod A00019
20DEC2006 HSCG23-07-J-ARP062 Delivery order for six RB-M, 45607 thru 45612 (two CLIN 1003A, four CLIN 1003B) and additional Project Management (three months of CLIN 3001)
14FEB2007 HSCG23-07-J-ARP097 Delivery order for two Display Models (CLIN 1005)
13NOV2007 HSCG23-07-J-ARP169 Delivery order for REA-012 "Keel Laying Ceremony" (Mod A00023, CLIN 1010)
24NOV2007 HSCG23-07-J-ARP169/A00001 Delivery order to change accounting data
25FEB2008 HSCG23-08-J-ARP094 Delivery order for eight RB-M, 45613 thru 45620 (CLIN 2003b) and additional Project Management (seven months of CLIN 3001)
25FEB2008 HSCG23-08-J-ARP108 Delivery order for ten RB-M, 45621 thru 45630 (CLIN 2003c)
18APR2008 HSCG23-08-J-ARP119 Task order specific to hull 45601 for Technical service (CLIN 2009)
9MAR2008 HSCG23-08-J-ARP120 Delivery order for spare and repair parts (CLIN 2008)
24NOV2008 HSCG23-08-J-ARP120/A00001 Delivery order to change accounting data
13NOV2008 HSCG23-08-J-ARP133 Interim funding for ECP-041 "PRO Green Bay" (Mod A00022, CLIN 1010)
24NOV2008 HSCG23-08-J-ARP133/A00001 Delivery order to change accounting data
18JUN2008 HSCG23-08-J-ARP187 Task order for Time and Materials (CLIN 3006) Technical Advice/Support
16OCT2008 HSCG23-08-J-ARP187/A00001 Task order to extend the Period of Performance (CLIN 3006)
19JUN2008 HSCG23-08-J-ARP199 Delivery order for spare and repair parts (CLIN 3008)
19JUN2008 HSCG23-08-J-ARP200 Task order for spare and repair parts (CLIN 2008)
16OCT2008 HSCG23-08-J-ARP200/A00001 Task order to extend the Period of Performance (CLIN 2008)
5AUG2008 HSCG23-08-J-ARP215 Task order to establish CLIN 1010 "Post award changes other then RB-M detailed design
25NOV2008 HSCG23-08-J-ARP215/A00001 Delivery order to change accounting data and correct typo of REA number
18DEC2008 HSCG23-08-J-ARP279 Delivery order for RB-M cradle as described in section C.7 (CLIN 3004)
14NOV2008 HSCG23-09-J-ARP016 Task order for increased video footage at a Coast Guard station (Mod A00021, CLIN 3007)
13NOV2008 HSCG23-09-J-ARP020 Task order for maintenance and support during accelerated operational effectivness evaluation of 45602 (Mod A00021, CLIN 3009)
16OCT2008 HSCG23-09-J-ARP019 Delivery order for spare and repair parts (CLIN 3008)
29OCT2008 HSCG23-09-J-ARP019/A00001 Change to Delivery order Requistion/Reference number