Orders Against the RB-M Production Contract

Date Order Number Description
21JUN2006 HSCG23-06-J-ARP019 Initial delivery order for Project Management (twelve months of CLIN 1001)
24AUG2006 HSCG23-06-J-ARP021 Delivery Order for Detailed Design of RB-M System (CLIN 1002)
17AUG2007 HSCG23-06-J-ARP021 A00001 Modifies delivery order to add interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
06SEP2007 HSCG23-06-J-ARP021 A00002 Modifies delivery order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18OCT2007 HSCG23-06-J-ARP021 A00003 Modifies delivery order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
11JAN2008 HSCG23-06-J-ARP021 A00004 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18MAR2008 HSCG23-06-J-ARP021 A00005 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
18MAR2008 HSCG23-06-J-ARP021 A00006 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
17SEPT2008 HSCG23-06-J-ARP021 A00007 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
7APR2009 HSCG23-06-J-ARP021 A00008 Modifies delivery Order to add additional interim funding for ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" (CLIN 1002)
21JUL2009 HSCG23-06-J-ARP021 A00009 This Modification A00009 to Delivery Order HSCG23-06-J-ARP021 funds the definitization of Engineering Change Proposal (ECP) ECP-009 entitled, "Interactive Electronic Technical Publication (IETP) and Maintenance Philosophy" to the negotiated total of $5,900,000 as for CLIN 1002 as changed by Modification A00033 to the Contract.
19JAN2010 HSCG23-06-J-ARP021 A00010 Pursuant to the authority of FAR Clause 52.242-15 "Stop-Work Order (AUG 1989)" the Contracting Officer hereby issues a "Stop-Work Order" ordering the Contractor to "stop work" on the effort ordered under Modifications A00001 through A00009 of this Delivery Order, effective immediately.
19APR2010 HSCG23-06-J-ARP021 A00011 The Contracting Officer hereby issues a "Partial Termination for Convenience of the Government" for all remaining performance effort for the work ordered under Modifications A00001 through A00009 of this Delivery Order.
25JUN2010 HSCG23-06-J-ARP021 A00012 Modifies delivery order to decrease price and deobligate $62,972.
15JUN2011 HSCG23-06-J-ARP021 A00013 Modifies delivery order to decrease price and deobligate $1,356,320.
23MAR2007 HSCG23-06-J-ARP032 Delivery Order for enhancements to Mock-Up (CLIN 1009)
08JUN2007 HSCG23-06-J-ARP032 A00001 Modifies delivery order for implementation of RB-M Agreement 1 (CLIN 1009)
30AUG2007 HSCG23-06-J-ARP032 A00002 Modifies delivery order to definitize REA-001 entitled, "Mock-Up Changes" (CLIN 1009)
5AUG2008 HSCG23-06-J-ARP032 A00003 Modifies delivery order to provide interim funding under CLIN 1009 as changed by Mod A00019
5JAN2009 HSCG23-06-J-ARP032 A00004 Modifies delivery order to provide funding of NRE for ECP-001 (Mod A00024, CLIN 1009)
9JAN2009 HSCG23-06-J-ARP032 A00005 Modifies delivery order to provide funding of NRE for ECP-006, ECP-007, ECP-008, ECP-013, ECP-020, ECP-026, ECP-028, REA-004 and REA-005 (Mod A00025, CLIN 1009)
9JAN2009 HSCG23-06-J-ARP032 A00006 This Modification is issued to provide funding of the Nonrecurring Engineering (NRE) for Engineering Change Proposal (ECP) ECP-037 entitled, "SINS Feed Power Modification" under CLIN 1009 as changed by Modification A00028. (Mod A00028, CLIN 1009)
27APR2009 HSCG23-06-J-ARP032 A00007 This Modification is issued to provide funding of the Nonrecurring Engineering (NRE) for Engineering Change Proposal (ECP) ECP-044 entitled, "Additional Weld & Hose Log Detail" under CLIN 1009 as changed by Modification A00032. (Mod A00032, CLIN 1009)
8JUL2009 HSCG23-06-J-ARP032 A00008 This Modification is issued to provide funding of the Nonrecurring Engineering (NRE) for Engineering Change Proposal (ECP) ECP-044 entitled, "Additional Weld & Hose Log Detail" under CLIN 1009 as changed by Modification A00035. (Mod A00035, CLIN 1009)
6AUG2009 HSCG23-06-J-ARP032 A00009 This Modification is issued to provide funding of the Nonrecurring Engineering (NRE) for Engineering Change Proposals (ECP) ECP-012, ECP-027, and ECP-032, and all costs for ECP-036, under CLIN 1009 as changed by Modification A00037. (Mod A00037, CLIN 1009)
17SEP2009 HSCG23-06-J-ARP032 A00010 This Modification is issued to provide funding for definitization of the Nonrecurring Engineering (NRE) for Engineering Change Proposal (ECP) ECP-044, "Additional Weld & Hose Log Detail," as changed by Modification A00039.
07JAN2011 HSCG23-06-J-ARP032 A00011 This Modification is issued to decrease the obligated amount of this Delivery Order by $237,275 from $1,115,050 to $877,775, as changed by Modification A00052.
08SEP2006 HSCG23-06-J-ARP033 Delivery Order for first RB-M, 45601 (CLIN 1003A) and additional Project Management (three months of CLIN 2001)
08SEP2006 HSCG23-06-J-ARP034 Delivery Order for five RB-M, 45602 thru 45606 (CLIN 1003A) and additional Project Management (nine months of CLIN 1002, three months of CLIN 3001)
20DEC2006 HSCG23-07-J-ARP062 Delivery Order for six RB-M, 45607 thru 45612 (two CLIN 1003A, four CLIN 1003B) and additional Project Management (three months of CLIN 3001)
14FEB2007 HSCG23-07-J-ARP097 Delivery Order for two Display Models (CLIN 1005)
16SEP2009 HSCG23-07-J-ARP097 A000001 Mod of original Delivery Order to provide funding for two additional RB-M Models (CLIN 4005)
23DEC2008 HSCG23-07-J-ARP137 Delivery Order to definitize ECP-001 "Main Engine Raw Water Cooling System Strainer" for Hulls 45601 - 45612 (Mod A00024, CLIN 1003ac and CLIN 1003bc)
4MAR2009 HSCG23-07-J-ARP137 A00001 Mod of original Delivery Order to change the accounting data
27APR2009 HSCG23-07-J-ARP137 A00002 Mod of original Delivery Order to provide interim funding of Recurring Expenses (RE) for pending Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45613 - 45620 only under CLIN 2003bc, as changed by Modification A00032
10JUL2009 HSCG23-07-J-ARP137 A00003 Mod of original Delivery Order to provide interim funding of Recurring Expenses (RE) for pending Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45621 - 45630 under CLIN 2003cc, and Hulls 45631 - 45636 under CLIN 3003cc, as changed by Modification A00036
3SEP2009 HSCG23-07-J-ARP137 A00004 Mod of original Delivery Order to provide interim funding of Recurring Expenses (RE) for pending Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45637 - 45666 under CLIN 3003dc, as changed by Modification A00038
13JAN2010 HSCG23-07-J-ARP137 A00005 Mod of original Delivery Order to add the correct accounting data for interim funding of Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45613 - 45630. A subsequent modification will delete the incorrect accounting data and reduce the value of this Delivery Order by $488,000.
3FEB2010 HSCG23-07-J-ARP137 A00006 Mod of original Delivery Order to delete the incorrect accounting data for interim funding of Engineering Change Proposal (ECP) ECP-001, entitled “Main Engine Raw Water Cooling System Strainer” for Hulls 45613 – 45630 and reduces the value of this Delivery Order by $488,000.
20SEP2010 HSCG23-07-J-ARP137 A00007 This Modification funds the definitization of Engineering Change Proposal (ECP) ECP-001 entitled “Main Engine Raw Water Cooling System Strainer” for Hulls 45613 – 45705, as definitized by Contract Modification A00047. The value of the delivery order is increased by $1,999,474.
07JAN2011 HSCG23-07-J-ARP137 A00008 This Modification funds the definitization of Engineering Change Proposal (ECP) ECP-006 entitled “Secure HF Communications Capability” for Hulls 45613 – 45666, and ECP-065 entitled "Grounding Wand" for Hulls 45613 - 45705, as definitized by Contract Modification A00051. The value of the delivery order is increased by $220,416.
21MAR2011 HSCG23-07-J-ARP137 A00009 This Modification funds the definitization of Non-Recurring (NR) costs for proposal preparation and incoporation of Onboard Spare Parts, and Recurring (RE) Costs for Onboard Spare Parts for Hulls 45656-45705, as incorporated by Contract Modification A00054. The value of the delivery order is increased by $34,834.
07APR2011 HSCG23-07-J-ARP137 A00010 This Modification provides funding for definitized changes for Hulls 45706-45715, as ordered in Delivery Order HSCG23-11-J-ARP126. The value of the delivery order is increased by $353,430.
12AUG2011 HSCG23-07-J-ARP137 A00011 Mod of original Delivery Order to add the correct accounting data for funding of Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45607 - 45612. A subsequent modification will delete the incorrect accounting data and reduce the value of this Delivery Order by $163,458.
20SEP2011 HSCG23-07-J-ARP137 A00012 Mod of original Delivery Order to deobligate the incorrect accounting data for funding in the amount of $163,458, for Engineering Change Proposal (ECP) ECP-001, entitled "Main Engine Raw Water Cooling System Strainer" for Hulls 45607 - 45612. This modification also provides funding in the amount of $412,005 for definitized changes for Hulls 45716-45726, as ordered in Delivery Order HSCG23-11-J-ARP238. The value of this delivery order is increased by $248,547.
17JAN2012 HSCG23-07-J-ARP137 A00013 Mod of original Delivery Order to apply credits due the Government on designated hulls, as incorporated by Contract Mods A00059 and A00060. Incorporate funding for ECP-183 Hatch Non-Skid and ECP-184 Hatch Hold Open Device for Hulls 45697-45705. The value of this delivery order is reduced by $60,560.
13NOV2007 HSCG23-07-J-ARP169 Delivery Order for REA-012 "Keel Laying Ceremony" (Mod A00023, CLIN 1010)
24NOV2007 HSCG23-07-J-ARP169 A00001 Delivery Order to change accounting data
23APR2009 HSCG23-07-J-ARP190 Delivery Order funds mod A00031, CLIN 1010
4JUN2009 HSCG23-07-J-ARP190 A00001 Delivery Order to correct the original Delivery Order. The amount of the Delivery Order should be $289,053, CLIN 1010
25FEB2008 HSCG23-08-J-ARP094 Delivery Order for eight RB-M, 45613 thru 45620 (CLIN 2003b) and additional Project Management (seven months of CLIN 3001)
25FEB2008 HSCG23-08-J-ARP108 Delivery Order for ten RB-M, 45621 thru 45630 (CLIN 2003c)
18APR2008 HSCG23-08-J-ARP119 Task Order specific to hull 45601 for Technical service (CLIN 2009)
9MAR2008 HSCG23-08-J-ARP120 Delivery Order for spare and repair parts (CLIN 2008)
24NOV2008 HSCG23-08-J-ARP120 A00001 Delivery Order to change accounting data
13NOV2008 HSCG23-08-J-ARP133 Interim funding for ECP-041 "PRO Green Bay" (Mod A00022, CLIN 1010)
24NOV2008 HSCG23-08-J-ARP133 A00001 Delivery Order to change accounting data
19FEB2009 HSCG23-08-J-ARP133 A00002 This Modification A00002 to Delivery Order HSCG23-08-J-ARP133 is issued to provide funding of the Nonrecurring Engineering (NRE) for Engineering Change Proposal (ECP) ECP-041 entitled, "Second PRO Facilities Modifications" as definitized by Modification A00027.
4JUN2009 HSCG23-08-J-ARP133 A00003 This Modification A00003 is an administrative change to Delivery Order HSCG23-08-J-ARP133 issued to correct Modification A00002. The unit price should be blank and the total amount of the Delivery Order should be $190,065. The correct amount of $190,065 was obligated in the Government's internal accounting system (CIMS), CLIN 1010.
18JUN2008 HSCG23-08-J-ARP187 Task Order for Time and Materials (CLIN 3006) Technical Advice/Support
16OCT2008 HSCG23-08-J-ARP187 A00001 Task Order to extend the Period of Performance (CLIN 3006)
17DEC2010 HSCG23-08-J-ARP187 A00002 Modifies task order to deobligate $5,000.
19JUN2008 HSCG23-08-J-ARP199 Delivery Order for spare and repair parts (CLIN 3008)
19JUN2008 HSCG23-08-J-ARP200 Task Order for spare and repair parts (CLIN 2008)
16OCT2008 HSCG23-08-J-ARP200 A00001 Task Order to extend the Period of Performance (CLIN 2008)
3JUN2009 HSCG23-08-J-ARP200 A00002 Task Order to increase the Not-to-Exceed amount by $10,000 from $25,000 to $35,000 (CLIN 3007)
11JUN2009 HSCG23-08-J-ARP200 A00003 Task Order modification to increase the Not-to-Exceed amount by $10,000 from $35,000 to $45,000. (CLIN 3007)
5AUG2008 HSCG23-08-J-ARP215 Task Order to establish CLIN 1010 "Post award changes other then RB-M detailed design
25NOV2008 HSCG23-08-J-ARP215 A00001 Delivery Order to change accounting data and correct typo of REA number
18DEC2008 HSCG23-08-J-ARP279 Delivery Order for RB-M cradle as described in section C.7 (CLIN 3004)
22SEP2008 HSCG23-08-J-ARP279 A00001 Delivery Order Modification to change the delivery address from Kent, WA to Green Bay, WI (CLIN 3004)
14NOV2008 HSCG23-09-J-ARP016 Task Order for increased video footage at a Coast Guard station (Mod A00021, CLIN 3007)
11NOV2009 HSCG23-09-J-ARP016 A00001 This Task Order Modification is issued to extend the Period of Performance from 05/30/2009 to 01/15/2010 (CLIN 3007)
22MAR2010 HSCG23-09-J-ARP016 A00002 Extend Period of Performance and Modify Accounting and Appropriation Data (CLIN 3007)
13NOV2008 HSCG23-09-J-ARP020 Task Order for maintenance and support during accelerated operational effectivness evaluation of 45602 (Mod A00021, CLIN 3009)
16OCT2008 HSCG23-09-J-ARP019 Delivery Order for spare and repair parts (CLIN 3008)
29OCT2008 HSCG23-09-J-ARP019 A00001 Change to Delivery Order Requistion/Reference number
27MAY2010 HSCG23-09-J-ARP019 A00002 Change to Delivery Order to increase NTE by $13,462.10 (CLIN 3008)
31MAY2011 HSCG23-09-J-ARP019 A00003 Change to Delivery Order to deobligate $83.33 (CLIN 3008)
20JAN2009 HSCG23-09-J-ARP061 Delivery Order for six RB-M, 45631 thru 45636 (CLIN 3003c)
18AUG2009 HSCG23-09-J-ARP061 A00001 Delivery Order modification to issue a change of the accounting data
23FEB2009 HSCG23-09-J-ARP069 Delivery Order which establishes a time period and Not-to-Exceed (NTE) value for ordering, processing, packing and providing spare, and repair parts for the RB-M system in accordance with Sections 080-2.2.2.3.3 and 080-2.4 of the Statement of Work (CLIN 3008 hulls 45609-45636)
18JUN2009 HSCG23-09-J-ARP069 A00001 Delivery Order which adds an item to fund retrofit parts to the Hull kits for Hulls 45601 - 45636 and also adds a revised Scope of Work and an updated List of Parts and Special Tools (CLIN 3008)
21DEC2008 HSCG23-09-J-ARP090 Task Order for Physical Configuration Audit (PCA) to deliver hull 45604 from Milwaukee to Green Bay and return to homeport (CLIN 3007)
11AUG2009 HSCG23-09-J-ARP090 A00001 This Modification to Task Order HSCG23-09-J-ARP090 is issued to increase the funding and Not-to-Exceed price by $1,389 from $17,500 to $18,889. All other terms and conditions of the Delivery Order remain unchanged. (CLIN 3007)
21DEC2008 HSCG23-09-J-ARP103 Task Order to provide transport of hull 45609 to San Juan, PR (CLIN 3007)
21DEC2008 HSCG23-09-J-ARP103 A00001 Task Order to cancel transport of hull 45609 to San Juan, PR
27APR2009 HSCG23-09-J-ARP178 Task Order to establish a time period and Not-to-Exceed value for Air Conditioning Alternatives Technical Study and Installation of Prototype. (CLIN 3007)
15OCT2009 HSCG23-09-J-ARP178 A00001 Task Order to revise the Period of Performance from 04/28/2009 thru 05/26/2009 to 04/06/2009 thru 01/29/2010. (CLIN 3007)
04JAN2011 HSCG23-09-J-ARP178 A00002 Task Order to deobligate excess funds. (CLIN 3007)
23MAR2009 HSCG23-09-J-ARP184 Delivery Order for thirty RB-M, 45637 thru 45666 (CLIN 3003d)
5MAY2009 HSCG23-09-J-ARP244 Task Order to establish a time period and Not-to-Exceed value for providing transportation of Hull 45613 to Maui, HI (CLIN 3007)
9JUN2009 HSCG23-09-J-ARP244 A00001 Task Order to replace the Scope of Work in its entirety for transportation of Hull 45613 to Maui, HI (CLIN 3007)
18JUN2009 HSCG23-09-J-ARP244 A00002 Task Order to raises the Not-to-Exceed amount by $13,000 from $50,000 to $63,000. (CLIN 3007)
5JUN2009 HSCG23-09-J-ARP268 Task Order to establish a time period and Not-to-Exceed (NTE) value for Engine Room Intake Ventilation Baffle Prototype and Testing on Hull 45602 (CLIN 3007)
20JUL2009 HSCG23-09-J-ARP268 A00001 Modification to Task Order incorporated revised scope of work
5JUN2009 HSCG23-09-J-ARP272 Task Order to establish a time period and Not-to-Exceed (NTE) value for Survivors' Compartment Joinery and Stowage Modification on Hull 45602 (CLIN 3007)
17JUN2009 HSCG23-09-J-ARP286 Task Order to establish a time period and Not-to-Exceed (NTE) value for over the phone or e-mail Technical Advice/Support in accordance with SOW 080-2.2.2.3.1. (CLIN 4006)
17DEC2010 HSCG23-09-J-ARP286 A00001 Modifies task order to deobligate $10,000.
17JUN2009 HSCG23-09-J-ARP288 Task Order to establish a time period and Not-to-Exceed (NTE) value for on-site technical services to repair or assist with repairs to the RB-M in accordance with Statement of Work Section 080-2.2.2.3.2. (CLIN 4007)
22DEC2009 HSCG23-09-J-ARP288 A00001 Task Order to deobligate excess funding from CLIN 4007 entitled Technical Services.
04JAN2011 HSCG23-09-J-ARP288 A00002 Task Order to deobligate excess funding from CLIN 4007 entitled Technical Services.
17JUN2009 HSCG23-09-J-ARP289 Delivery Order to establish a time period and Not-to-Exceed (NTE) value for ordering, processing, packing and providing spare, and repair parts for the RB-M system IAW Sections 080-2.2.2.3.3 and 080-2.4 of the SOW. (CLIN 4008)
17DEC2010 HSCG23-09-J-ARP289 A00001 Modifies delivery order to deobligate $1,929,353.49.
3AUG2009 HSCG23-09-J-ARP292 Delivery Order for Project Management. (CLIN 5001)
6AUG2009 HSCG23-09-J-ARP322 This Delivery Order funds the definitization of Request for Equitable Adjustmant (REA) REA-018 entitled, "Technical Support of Puerto Rico Delivery" as incorporated by Modification A00037, at the negotiated price of $3,165. PR #21-09-239ARP322. (CLIN 1010)
17SEP2009 HSCG23-09-J-ARP322 A00001 This Modification definitizes Request for Equitable Adjustment (REA) REA-019, entitled, "Cost to Prepare Engineering Change Proposals (ECP) ECP-060" (Modification A00039, CLIN 1010)
4JAN2010 HSCG23-10-J-ARP083 This Task Order establishes a time period of 12 January 2010 - 14 January 2010 and Not-to-Exceed (NTE) value of $17,500 for Maintenance and Electrical/Control Familiarization (CLIN 4007)
13SEP2011 HSCG23-10-J-ARP083 A00001 This Task Order Modification changes the Not to Exceed (NTE) to read $0, and deobligates $17,500.
22APR2010 HSCG23-10-J-ARP138 Delivery Order for thirty RB-M, 45667 thru 45696 (CLIN 4003e) and Project Management (CLINs 6001 and 7001).
01FEB2011 HSCG23-10-J-ARP138 A00001 Delivery Order Modification to correct Period of Performance end date to 31 JUL 2012.
22JUN2010 HSCG23-10-J-ARP212 Delivery Order for nine RB-M, 45697 thru 45705 (CLIN 5003f) and Project Management (CLIN 7001).
27OCT2010 HSCG23-10-J-ARP277 Delivery Order for 12 Stowage Cradles (CLIN 5004a) and Stowage Cradle Design (CLIN 5004c).
25MAY2011 HSCG23-10-J-ARP277 A00001 Delivery Order Modification to increase Stowage Cradle price (CLIN 5004a).
4JUN2010 HSCG23-10-J-POEW22 Task Order for Technical Services (CLIN 4007a)
18JUN2010 HSCG23-10-J-POEW22 A00001 Modification to Task Order to revise Contracting Officer's Authorized Representatives list
20OCT2010 HSCG23-11-J-POEX05 Task Order for Technical Services (CLIN 5007b)
13JAN2011 HSCG23-11-J-POEX05 A00001 Modification to Task Order to revise Contracting Officer's Authorized Representatives list.
18FEB2011 HSCG23-11-J-POEX05 A00002 Modification to Task Order to increase funding.
13SEP2011 HSCG23-11-J-POEX05 A00003 Modification to Task Order to revise Contracting Officer's Authorized Representatives list.
07APR2011 HSCG23-11-J-ARP126 Delivery Order for ten RB-M, 45706 thru 45715 (CLIN 5003f) and Project Management (CLIN 7001).
20SEP2011 HSCG23-11-J-ARP238 Delivery Order for eleven RB-M, 45716 thru 45726 (CLIN 6003f) and Project Management (CLIN 7001).
13OCT2011 HSCG23-12-J-POE000 Task Order for Technical Services (CLIN 6007b).
21DEC2011 HSCG23-12-J-ARP400 Delivery Order to provide funding for Recurring Expenses (RE) on CLIN 4003ep for ECP-183 Hatch Non-Skid for Hulls 45684-45696, and ECP-184 Hatch Hold Open Device for Hulls 45685-45696, and Cost to Prepare (CTP) and Non-Recurring Engineering (NRE) on CLIN 6002 for ECP-183 and ECP-184.
25OCT2011 HSCG23-12-J-ARP403 Delivery Order for nine Stowage Cradles (CLIN 6004).